Water Treatment Plant - Moody Air Force Base,
Moody Air Force Base, GA

Design/Build & Construction Services

cs_acoe_water_treatmnt_moody.jpg

SCOPE OF SERVICES

This Design-Build services project was the first Nanofiltration Water Treatment Plant placed in service in the State of Georgia. The work included the construction of a facility containing two (2) membrane filtration skids with the capability of 1 MGD with fully automated controls, and with future expansion capabilities for two (2) more skids to provide a total of 2 MGD capacity. The work included demolition of the old cascading tray water and construction of new packed tower aerator. The work also required replacing three submersible deep well pumps and motors and installing a 600 amp breaker and service for emergency backup power.

MANUFACTURING / INDUSTRIAL
WATER TREATMENT


GENERAL CONTRACTOR:

Harry Pepper & Associates, Inc.

CLIENT:
Army Corps of Engineers –
Savannah District
Moody Resident Office
2485 Georgia Street, 918
Moody AFB, GA 31699
Contact: Brian Doak,
Project Engineer
Phone: 229.257.2149

PROJECT DURATION:
April 20, 2001 –
September 20, 2002

CONTRACT AMOUNT:
$2,915,537

 

Harry Pepper & Associates - Technical solutions, Relationships, Quality Service, Value Engineering, Experience, Project Schedule & Coordination, Expertise

 

case_box_check.gif Design/Build
case_box.gif Bid Build
case_box_check.gif New Construction
case_box.gif Retrofit/Renovation
case_box.gif Electrical Construction
case_box_check.gif Mechanical Construction
case_box.gif Facilities Services
case_box.gif Consulting Services
case_box.gif HVAC Services