Dock 146, Naval Support Activity, Panama City, FL

Design/Build Construction Services

SCOPE OF SERVICES

Design / Build Services - The project will make necessary repairs to the facility including structural deficiencies, new steel sheet pile for the entire length of the dock, constructing a new concrete cap, constructing two new crane loading zones, replacing utility trench covers running alongside the dock, repairs to the utility trench, repairing/replacing deteriorated utilities to five "Utility Box" stations along the dock, replacing all concrete pavement and concrete utility boxes, and installing an impressed current cathodic protection system. Boat slip cover (building 302) shall be removed and refurbished or removed and replaced to facilitate installation of underlying sheet pile. The existing facility is a 2,125 foot long (648 meter long) concrete dock with 11,898 SY (9,948 M2) of dock space constructed circa 1953.

PUBLIC / GOVERNMENT
MILITARY


GENERAL CONTRACTOR:

Harry Pepper & Associates, Inc.

CLIENT:
NAVFAC SE, PWD, ROICC
101 Vernon Avenue
NSA Panama City, FL 32407
Contact: Robert A. Arnold
Phone: 850.234.4736

PROJECT DURATION:
June 30, 2008 – Jan 6, 2010

CONTRACT AMOUNT:
$14,015,658.00

 

Harry Pepper & Associates - Technical solutions, Relationships, Quality Service, Value Engineering, Experience, Project Schedule & Coordination, Expertise

 

case_box_check.gif Design/Build
case_box.gif Bid Build
case_box_check.gif New Construction
case_box_check.gif Retrofit/Renovation
case_box.gif Electrical Construction
case_box.gif Mechanical Construction
case_box.gif Facilities Services
case_box.gif Consulting Services
case_box.gif HVAC Services